Description
GIS Engineering & Environmental Services was entrusted with the full execution of 4 parallel fuel transfer pipelines connecting KOJ (Kurasini Oil Jetty) to the Sahara Energy Depot. The project was part of a strategic infrastructure improvement to increase petroleum product transfer efficiency and minimize vessel turnaround time at port. The installation was completed under strict safety, regulatory, and environmental guidelines.
Client: Sahara Tanzania Limited
Project Title: Piping Works from KOJ to Sahara Depot – Installation of 4 Fuel Transfer Lines
Location: Dar es Salaam Port Zone, Tanzania
Sector: Oil & Gas Logistics Infrastructure
Service Category: Pipeline Engineering, Fuel Transfer Systems, Civil & Mechanical Works
Problem
Due to increased fuel throughput and traffic at the Dar es Salaam Port, Sahara Depot required high-capacity, efficient, and environmentally safe fuel transfer lines directly from KOJ. The primary challenges included:
-
Working in a high-risk, operational oil zone
-
Navigating a congested pipeline corridor with multiple utility crossings
-
Coordination with TPA, SUMATRA (now TASAC), and environmental authorities
-
Need for tight schedule adherence to minimize port disruption
Solution
GIS provided turnkey pipeline design and installation services, covering all engineering, mechanical, and compliance aspects. Our solutions included:
-
Engineering design for 4 parallel above- and underground transfer lines
-
Installation of pipe supports, expansion loops, and valve chambers
-
Pressure testing and hydrostatic testing of each line
-
Environmental and social mitigation planning
-
Construction of protective encasements at critical crossings
Process
-
Route Survey & Utility Mapping
Identified and coordinated existing pipeline networks to avoid service disruption. -
Pipe Fabrication & Trenching
Precision welding and coating of fuel-grade pipes followed by trench excavation and bedding. -
Valve & Manifold Installation
Deployed inline valves, air-release points, and flow control systems at strategic locations. -
Testing & Commissioning
Conducted pressure and leak tests on all 4 lines in compliance with international standards. -
Environmental Monitoring & Safety Oversight
Implemented spill prevention plans and trained staff on safety compliance.
Results
-
4 fully operational fuel transfer lines commissioned
-
Reduced vessel offloading time by 30% at KOJ
-
Full compliance with EWURA, NEMC, and port safety standards
-
Enhanced depot fueling capacity and throughput efficiency
-
Zero incidents reported during project execution